Expectations about Dangote Refinery inauguration are Extremely Exaggerated

Must read

By the Editorial Board of Africa Oil+ Gas Report

The ceremony around the planned visit by the Nigerian President to the Dangote Refinery on May 22, 2023, will peak with a cutting of the ribbon, ‘inaugurating’ the 650,000Barrels per Stream Day Plant, located in the eastern flank of Lagos, the country’s commercial city.

Everyone, it seems, looks forward to production of petroleum products from the plant after that symbolic activity.

But it will not happen.

As President Muhammad Buhari leaves office a week after

“commissioning” of one of the largest, single train hydrocarbon processing plants on the planet, he could be forgiven for believing he had had his wish to be in such a large place, but technology does not sit well with politics.

The ongoing technical commissioning process has not gotten anywhere close to the point of introducing raw hydrocarbon into the plant, let alone delivering petroleum products.

One key challenge of Nigeria’s chattering classes is that they hardly look up the regulation. Hydrocarbon will be introduced only when the Nigerian Midstream Downstream Petroleum Regulatory Agency (NMDPRA) approves and issues License To Operate the Refinery to Dangote.

Speculations about ‘inauguration’ and ‘commissioning’ are just, well, speculations. Both words do not appear anywhere in the ‘Procedure to License A Refinery’ in Nigerian law. The three stages are:

1. License to Establish a Refinery

2. Approval to Construct the Refinery

3. License to Operate the Refinery.

Nowhere does inauguration or commissioning appear. So, the Refinery can be inaugurated or commissioned as the Licensee desires, as long as no attempt is made to operate the Refinery by introducing crude oil and make products For Sale, it does not concern NMDPRA.

We live in a society where optics trumps everything. Buhari has been President for 8 out of the 9 years that the Refinery Project has been on. What is wrong with Dangote asking President Buhari to inaugurate the Refinery, so his name is on the marble when the facility becomes fully functional? Afterall no law will be breached by such a gesture?

That said, Aliko Dangote, the billionaire owner of the refinery, is determined that the $19Billion project, the second of his three, hydrocarbon processing mega projects (Fertiliser, Refinery and Petrochemicals) is delivered by end of 2023.

The technical work has gone far: involving trial-running every single equipment, which has taken a while because of the length time of mechanical construction. Some equipment were installed six years ago, and were just standing there, in the air, water or even underground. Anything, literarily, could have happened.

As of February 2021, the installation of the Crude Distillation equipment had been completed.

So had the kitting up of the Residue Fluid Catalytic Cracking Unit (RFCCU).

Supply chain challenges thrown up by the COVID- 19 did slow down work, but the construction of Africa’s largest hydrocarbon processing factory picked up steam again in mid-2021.

“The electricals and instrumentation works are usually invisible to the gaze of non-refinery workers, but they are key: their installation needed extreme care and it consumes over 30% of the refinery construction time,” say several managers familiar with the project.

“A lot of our contractors are Chinese. Those who went home couldn’t come back quickly, but the project workflow recovered and those installations, especially that of the Crude Distillation Column, which arrived Nigeria in December 2019, were expedited”.

“We will have 15 process units in the refinery, and they must all work together”, the managers tell us.

The operations planning will emphasize the mantra at the commissioning: “We must flow everything out with air, then do it with water, then with steam, then with air again”. This is all to ensure that the likelihood of moisture absorption is zero, as the contrary will lead to cracks.

“The equipment must be pickled. What that does is that it oxidizes the facility”.

The Dangote Refinery is significantly an Indian supervised operation.

But a significant percentage of the 1,000 Nigerian engineers sent to training in India for the eventual operations of the facility, have returned and are currently engaged on site.

The relationship between the Nigerian crude oil refining sector and Indian engineering expertise goes back as far as 1988, when the second (larger) refinery in Port Harcourt, the major city in the country’s oil producing Delta region, was being constructed.

“Some of the experts working on ‘Operations Planning’ were part of the construction of the Port Harcourt Refinery 35 years ago”, our sources say.

Mr. Dangote initially announced the likelihood of the project in

2013. But it was at the All-Convention Luncheon at the annual conference of the Nigerian Association of Petroleum

Explorationists (NAPE) in November 2014, that he provided the first relatively comprehensive details of the facility. He told the roomful of geoscientists that the capacity had increased from 500,000BSPD to 650,000BPSD

Dangote Industries was advised by Jacobs Engineering and it licensed the Honeywell UOP for the basic engineering design. On a daily basis, the facility will have the capacity to produce 59 Million litres of gasoline; 20Million litres of Kerosene, Nine Million litres of Diesel and others.

The construction has taken a while and has been though the most excruciating economic challenges Nigeria has ever faced. Would Dangote Industries have delivered this project much earlier if it had awarded it to a world-class EPC contractor like Bechtel, TechnipFMC, Siemens, KBR?

“Yes”, said Alex Ogedengbe, a retired Group Executive Director (GED) at the NNPC, who was involved in the construction of the Warri and Port Harcourt Refineries in the 1980s. “There are just about six or seven such EPC contractors in the world”, he explained. Mr. Ogedengbe was speaking at a private webinar, organized by oil and gas analyst Ronke Onodeko, in April 2020.

Dangote sources maintain that the cost would have been at least 30% higher if that route had been taken. And while it could be argued that Dangote Industries could have had good value for money if a Bechtel or a KBR had handled the construction, multiple sources argue that the delay could have been minimized if the current structure had been in place since inception. The company went into this project with the mindset of constructing a cement plant, which was its major competence before this huge assignment. “We wasted the most time at the engineering stage”, one manager recalls. “A reputable EPC contractor would still have hired expertise from outside like we are doing and subcontract several units. Dangote Industries bought brand new equipment for this work; an EPC contractor might not even have done that, but it would have coordinated things better at the outset”.

One more advantage of building it yourself: all the equipment you purchase for logistics and construction purposes are yours.

Everyone we spoke to agreed that things began to take very good shape when Giuseppe Surace came along. The Italian engineer who had been Chief Executive of Saipem in Nigeria and Brazil, joined the project in June 2017 as Chief Operating Officer. “On the factory floors, in the executive offices, everywhere on site, the consensus is that one of the best decisions that Aliko Dangote made was Surace’s appointment”, said our sources. “He saved the project”.

A highlight of the swirling speculations around President Buhari’s impending visit is the description of how crude oil will be pumped into the refinery. One widely circulated message confidently talks of a “large sub-sea pipeline infrastructure connected to Oil and Gas blocks in the Niger Delta region for supply of crude feedstock”.

That’s a false narrative.The truth is that Single Point Mooring s (SPM) buoys will play a huge role in input crude delivery and output petroleum products.

There are three of them either way. Three SPMs will deliver the input crude oil from vessels into a jetty from which it is pumped into the plant. And three SPMs will ferry petroleum products out to vessels on the sea for export. “We have facility to evacuate through roads, we have a large loading capacity (103 loading terminals) and we can evacuate 75% of our production through road and we can also evacuate 75% of our production through the sea so that if we want to export”, Dangote officials have repeatedly explained.

“Within Nigeria we can evacuate to Warri, Port Harcourt, Calabar and so on, those options are available”, the officials say.

On the table is the idea of a six-lane road through Epe, a town in the east of Lagos. But what of the supply of the product to Lagos?

Will some of it be through the Lekki Expressway? The subject of the quality of Nigerian roads to take in the products, through land tankers, is still a fraught one.

Source: Africa oil + Gas report